Posts Tagged ‘payment bond’

Trumbull and Berks Products Payment Bonds

Pennsylvania’s Prompt Payment Act states that “once a contractor has made payment to the subcontractor . . . claims for payment against the contractor or the contractor’s surety by parties owed payment from the subcontractor . . . shall be barred.” The Contractor and Subcontractor Payment Act provides similar (but slightly different) language. This is referred to as the “safe harbor” clause.

In 2001, to the pleasure of the bonding industry, the Pennsylvania Commonwealth Court opined that the general contractor’s payments to the subcontractor barred a claim by the sub-subcontractor on the payment bond. Trumbull Corp. v. Boss Const. Inc., 768 A.2d 368. The court held that the Prompt Payment Act’s language absolved both the contractor and the surety of liability. Even though the subcontractor failed to pay a sub-subcontractor, the claim on the bond was dismissed.

But in 2013, under similar circumstances, the Pennsylvania Commonwealth Court held that the general contractor’s payments to the subcontractor did not afford protection, and the Prompt Payment Act did not shield the contractor and the surety from liability. Berks Products Corp. v. Arch Ins. Co., 72 A.3d 315.

The 2013 Berks Products case was widely seen as abrogating the Trumbull decision, and taking away the “safe harbor” provided by the Prompt Payment Act. But a close reading of Berks Products indicates that the Prompt Payment Act’s barring of claims will still be enforced—so long as the bond language is carefully written:

[T]he payment bond drafted by [Surety] . . . provided that the bond shall remain in full force and effect until such time as both [General Contractor] and any subcontractor . . . make full payment for any labor and/or materials . . . .

* * *

[Sub-subcontractor] was entitled to seek recovery under the Bond Law, and the “safe harbor” provision would generally be applicable to [General Contractor]. However, an issue arose as to whether the language of the payment bond . . . waived this provision.

Point being: the Prompt Payment Act’s “safe harbor” clause is still effective. But the bond should be written carefully, to reflect that payment from the Contractor will extinguish the bond obligations. If the bond states that payment by the Contractor and all Subcontractors will extinguish the bond, then, the court might treat it as a Berks Products bond, and hold that it waived the “safe harbor” provision.

When issues pertaining to payment bonds arise, it is best to seek legal advice early and often.

 

What’s Happening Now . . .

Residential Construction

  • Indicators of new residential construction were improved, comparing Feb. 2016 to Feb. 2015.
  • Building Permits: Feb. 2016 is 6.4% above Feb. 2015.
  • Housing Starts: Feb. 2016 is approx. 30.9% above Feb. 2015.
  • Housing Completions: Feb. 2016 is 17.5% improvement.

Source: U.S. Census Bureau News, New Residential Construction in February 2016, U.S. Dept. of Housing (Mar. 16, 2016).

Newsletter written by Jeffrey C. Bright, Esq. , an attorney licensed in Pennsylvania and Maryland. For more information, contact an attorney at Harmon & Davies, P.C.

Tags: , , , , , , , , , , , , , ,
Posted in Construction | Comments Off on Trumbull and Berks Products Payment Bonds

Legal Punchlist November 2015

Legal Punchlist Newsletter (Nov. 2015)

Tags: , , , , , , , , , , , , , , , , , , ,
Posted in Construction | Comments Off on Legal Punchlist November 2015

A Quick Reference Guide to Pennsylvania Mechanics’ Lien Laws

Disclaimer:  This fact sheet pertains only to the Mechanics’ Lien Law of Pennsylvania.  Other states, including Maryland, New Jersey, and Delaware have dramatically different Mechanics’ Lien Laws.

What is a mechanics’ lien?  A security interest in the title to a property for the benefit of those who have supplied labor or materials to the property.  In other words, it’s a tool to help contractors, subcontractors, and suppliers ensure payment. 

Obviously subs/suppliers care about mechanics’ lien rights, but what about GCs?  Most contracts with owners require GCs to defend and bond off mechanics’ lien claims.  Therefore, on a basic level you need to know: (1) what mechanics’ liens are; (2) how to avoid them (get a list of all subs/suppliers and make sure everyone is getting paid for the labor and material they supply); (3) how to defend against them (did the claimant follow all the procedures for perfecting a lien within the allotted time?); and (4) how to bond them off.

On rare occasions, a GC might need to file a mechanics’ lien claim to secure its right to payment.  In this event, you need to know how to preserve your claim.

Who can file a lien? General contractors, subcontractors and sub-subcontractors (i.e. contractors and suppliers who have a direct contract with subcontractors).  No one below the level of a sub-subcontractor has lien rights.

When to file a lien?  Subcontractors (but not general contractors) must provide the owner with what is referred to as a formal notice of intent to lien.  This formal written notice must be provided to the owner at least 30 days before the lien claim is filed by a subcontractor or supplier.

All claimants must file their lien claim within six months of the claimant’s last date of work.

How do I determine the last date of work? Time limits to file a claim or serve a formal notice of intent to lien are based on the date of completion of the claimant’s work, not from the date of completion of the entire project.  The work is complete when the claimant has performed the last of the labor or delivered the last of the materials required by the terms of the claimant’s contract.  [Note: claimants cannot tack on additional material or labor to a contract for the purpose of extending the time to file a claim.  It is prudent to count deadlines from the last substantial new work.  Warranty work and repair work may not extend the filing deadlines.]

What must a subcontractor include in its formal notice of intent to lien?

  1. Name of claimant
  2. Name of the person with whom claimant contracted;
  3. The amount claimed;
  4. The general nature and character of the labor or materials furnished;
  5. The date of completion of claimant’s work; and
  6. A description of the property. 

 

What happens after a lien claim is filed?  Within one month after the initial claim filing, written notice of the filing of the lien must be served on the owner, typically by the sheriff.  Thereafter, the claimant has 20 days to serve an affidavit of service with the court.

After the above steps have been taken, no further action is immediately necessary.  However, within two years of filing the claim, the claimant must file a complaint to enforce its claim.

Does a mechanics’ lien require any pre-filing before construction? No.

Can a public project be liened? No.  Liens are not allowed for labor or material furnished for a purely public purpose.

What is the minimum amount for a lien claim?  $500.00.

Can lien rights be waived?  Yes, but certain procedures need to be followed as Pennsylvania has declared lien waivers to be void as against public policy.

On all projects, a subcontractor can waive its rights to file a lien only if the general contractor provides a bond guaranteeing payment to subcontractors, i.e. a payment bond.  As long as a payment bond is in place, a general contractor may file a stipulation against liens with the prothonotary’s office in the county where the project is located.  To be effective, a stipulation against liens should be filed: (1) prior to commencement of work on the ground; (2) within 10 days after execution of the principal contract; or (3) not less than 10 days before the contract with the subcontractor.  Moreover, the lien stip must be indexed in the name of the general contractor and owner of the property.  Although the GC does not have to provide its subs/suppliers with a copy of the Stipulation Against Liens, it is a good practice to do so because this way the GC ensures that its subs/suppliers actually receive notice.

A subcontractor can also waive lien rights in exchange for progress payments received on a project.

Is there a way to remove a lien?  Yes.  A lien against the property may be removed by petitioning the court to discharge the lien by depositing the amount of the lien with the court or by posting a bond in double the amount of the lien.

Is payment a defense to a mechanics’ lien claim?    There is no automatic “defense of payment” for the owner.  The owner can be required to pay for a project twice.  But the owner can protect itself by recording a copy of the general contract or stipulation in the prothonotary’s office before commencing construction.  This will limit each subcontractor to a pro-rata share of money still owed to the general contractor.

Why might a mechanics’ lien be preferred over filing a breach of contract complaint in court?  A mechanics’ lien creates a better security interest.  In the event of the owner’s bankruptcy, the automatic stay of the United States Bankruptcy Code does not stay perfection of the mechanics’ lien claim for new construction.  This is because a lien claim “relates back” to the time when work visibly commenced on the project.  Moreover a mechanics’ lien has priority over all liens on a property (except an acquisition or construction loan).  Additionally, lien rights survive any foreclosure or sale of property (except foreclosure on an acquisition or construction loan).

Accordingly, if the owner’s finances appear to be precarious and a contractor is not getting paid, a mechanics’ lien might be the best mechanism for protecting the contractor.

This article is authored by attorney Shannon O. Young and is intended for educational purposes and to give you general information and a general understanding of the law only, not to provide specific legal advice. Any particular questions should be directed to your legal counsel or, if you do not have one, please feel free to contact us.

 

Tags: , , , , , , , , , , , , , , , , , , , , , , , , , , , , ,
Posted in Construction, Mechanics' Liens | No Comments »

 

  1. What is a performance bond?

Generally, a performance bond assures an obligee (usually an Owner/General Contractor) that if the principal fails to perform, the surety will discharge the principal’s obligations either through performance or by paying the obligee the excess cost of performance.  Performance bonds differ from payment bonds (sometimes called labor and materials bonds), which are put in place to ensure that laborers, subcontractors, and suppliers are paid.

By way of example, where a performance bond is in place, a general contractor may file a performance bond claim with a surety when a subcontractor defaults.  It isn’t enough for a party to simply assert a claim under a performance bond.  Rather, a claiming party must heed the requirements of the performance bond.  Particularly, a claiming party needs to pay attention to the deadline for initiating litigation to enforce a bond claim or else the claim may be lost.

 

  1. The Timeliness of a performance bond claim. 

As a general rule in Pennsylvania, the statute of limitations for asserting an action on a performance bond or payment bond is one yearSee 42 Pa.Cons.Stat. §5523(3).  However, under Pennsylvania law, parties to a contract may contractually agree to shorten a statute of limitations period.  In Kedar Corp. v. American Contractors Indemnity Company, a case decided just last month by the Eastern District of Pennsylvania, the time period for filing a performance bond had been contractually shortened to six months.  [Of note: six months is considered a permissibly reasonable contractual limitations period under Pennsylvania law, but if one is dealing with a performance bond issued on a federal project, a six month duration within which to file a bond claim most likely would not be upheld under federal law.]

 

  1. The doctrine of fraudulent concealment based on a theory of estoppel may save an otherwise untimely bond claim.  

In the Kedar Corp. case, the surety defended the contractor’s performance bond action by arguing that it was untimely because the action had not been filed within six months after the subcontractor defaulted.  The surety moved for summary judgment (an early dismissal of the case) on this basis.  In response, the contractor successfully argued that its claim was not untimely by asserting a doctrine developed in Pennsylvania known as the doctrine of fraudulent concealment based on a theory of estoppel (the “Doctrine”).

The Doctrine tolls (a/k/a suspends) the statute of limitations where, through fraud or concealment, the defendant causes the plaintiff to relax his vigilance or deviate from the right inquiry; some sort of affirmative act of concealment that would divert or mislead the plaintiff from discovering the injury is required.   In other words, if the defendant was merely silent, the Doctrine won’t apply.  The Pennsylvania Supreme Court has recognized that any act which tends to mislead the plaintiff, while parties are dealing on friendly terms, to avoid litigation, will be held to be evidence of a waiver of the contractual limitations period.

In Kedar Corp., the contactor successfully defeated summary judgment by arguing that a course of dealings existed between the contractor and the surety whereby the contractor was led to believe that the performance bond’s six month limitations period would not be enforced by the surety.  There, the contractor notified the surety of the subcontractor’s default in September 2009 and made an unequivocal demand for the surety to honor its obligations under the performance bond.  After November 2009, little, if any, communication took place between the contractor and surety.  In May 2010 the contractor completed the work on the project.  By October 2010, the surety and contractor resumed their discussions regarding the contractor’s demand for payment on the performance bond with no indication by the surety that it intended to assert that the contractor’s claim was untimely.  In July 2011, the surety averred that the contractor’s claim was submitted more than six month’s after the sub’s default and, therefore, untimely.

The court found that although the record did not show that the surety expressly waived enforcement of the limitations period or definitely acknowledged liability in this case, its conduct was such as to reasonably convey that the limitation period would not be strictly enforced as the parties pursued settlement opportunities.  The court acknowledged the lack of documented communications between the parties for a period of time, but recognized that: (1) a demand for payment had already been made; (2) the parties had begun a course of discussions regarding that demand; (3) surety was aware of the plaintiff’s ongoing work on the project; (4) the surety never indicated that contractor should cease work on the project; and (5) no definitive payment on the performance bond could be made until the plaintiff completed the project in May 2010. Moreover, the Court noted that the surety promptly resumed negotiations with contractor in October 2010, which was directly contrary to any intent to enforce a time bar.

 

  1. Conclusion

 If you are an owner or contractor and a surety tries telling you that your bond claim is untimely, don’t tuck your tail and run if the surety led you to believe that your claim could be worked out to the point where you felt like pursuing litigation to recover on the bond claim was unnecessary.  However, under such circumstances, it is strongly recommended that you consult with an attorney before your filing deadline expires.  The attorneys at Harmon & Davies are available to assist with bond claims.

This article is authored by attorney Shannon O. Young and is intended for educational purposes and to give you general information and a general understanding of the law only, not to provide specific legal advice.  Any particular questions should be directed to your legal counsel or, if you do not have one, please feel free to contact us.